Building
Status as on 06-05-2008
Click here to view the pictures of Model Flat
| Block A |
| Foundation |
: |
Completed. |
| Casting |
: |
Salballa shouring - Completed, Basement - Completed, Retention wall - Completed, Ramp casting - Completed, Deck slab Completed, Ground floor roof slab - Completed, 1st floor roof casting - Completed. 2nd Floor roof casting - Completed. 3rd Floor roof casting - completed. 4th floor roof casting completed, 5th Floor column casting completed. 5th floor roof slab shuttering work completed, rod binding continuing. |
| Brickwork & Plaster |
: |
1st & 2nd floor completed and 3rd floor continuing. |
| Elevation |
: |
1st, 2nd and 3rd floor continuing. |
| Plumbing |
: |
1st & 2nd floor completed (kitchen & toilet) 3rd floor continuing (kitchen & toilet) and water proofing - 1st & 2nd floor (Toilet area) completed. |
| Electricals |
: |
Conduit Pipe dressing & box fixing- 2nd floor completed and 3rd floor continuing. |
|
|
| |
|
| Block B |
| Foundation |
: |
Completed. |
| Casting |
: |
Salballa shouring - Completed, Basement - 100%Completed with water proofing & plastering of Retention wall - Completed, Ramp casting - Completed, Deck slab casting Completed, Ground floor roof slab - Completed, 1st floor roof casting - Completed. 2nd Floor roof casting - Completed. 3rd Floor roof casting - completed. 4th floor roof casting completed, 5th Floor column casting completed. 5th floor roof slab work completed. Model Flat-Completed (Flat 1F) |
| Brickwork & Plaster |
: |
1st, 2nd, 3rd & 4th floor completed & 5th floor continuing of brick work. Plaster- 1st, 2nd 3rd floor completed & 4th floor continuing. |
| Elevation |
: |
1st, 2nd, 3rd, 4th & 5th floor continuing. |
| Plumbing |
: |
1st & 2nd floor completed (kitchen & toilet) 3rd floor continuing (kitchen & toilet) and water proofing - 1st & 2nd floor (Toilet area) completed. 3rd floor continuing. |
| Electricals |
: |
Conduit Pipe dressing & box fixing- 2nd floor completed and 3rd floor continuing. |
|
|
| |
|
|